Grading Done and Columns Installed

churchnov09.JPG

Fall 2009

11_10_09-3.jpgNovember 2009 moving dirt11_10_09-2.jpg

11/18/2009 and no snow in Kalkaska yet! Work has continued, altho slowly. We have applied for a grant that would help us work on the interior of the building through the winter and we are anxiously awaiting the outcome of the application.

Last week the big equipment came in and began “moving dirt” - moving dirt from the back parking areas to the the front much higher areas. 

November Break in the Weather!

siding3.jpeg

Siding is going up on Nov. 5

November 5 - Siding is going up! 

siding.jpeg

siding2.jpeg

siding4.jpeg

WOW - doesn’t that look GREAT!!!

November 2, 2007 Cement Work

Hard Hat Homecoming October 12, 2008

hhh11.jpeghhh10.jpeghhh9.jpeghhh8.jpeghhh6.jpeghhh5.jpeghhh2.jpeghhh1.jpeghhh3.jpeghhh4.jpeghhh7.jpeg

An evening of fun, prayer and fellowship was held on Sunday evening, Oct. 12. The whole church familyl was invited to tour the new construction site, write thoughts, scriptures, and prayers on the unfinished walls, floors and studs, and have questions answered. Then we all met at the bonfire for a time of singing. We then formed a large prayer circle and Dean Farrier closed out our time together with prayer. Many wonderful comments came out of the evening, included one gal who emailed: “I must tell you, walking in to the basement of the church tonight…I was almost in tears. God has blessed this congregation so abundantly and you could truly feel His presence in that building. It was almost overwhelming. I fought off the tears all night - good tears. I feel so lucky to be a part of this church body, I can’t even tell ya.”

September 10 update

Well, here is Kalkaska we had frost this morning! But the sun was shining and it was a beautiful day to take a few updated photos of the progress at the construction site.sep08-001copy.jpg

The side view - windows are installed on the main floor.

sep08-004copy.jpg

The lower level inside - lots of space!

sep08-007copy.jpg

There’s a bit of fill yet to be moved to create the drop off area under the “porch”.  Plans are to have the shell completed by mid November and then work will cease until spring.

sep08-009copy.jpg

As always, the prayer bench is under the tree - feel free to go there anytime and pray for the future of the church in Kalkaska and pray for the construction, as well.

We’re building a church and building a building!!

August 7 - trusses are going up!!

trussescopy.jpgtrussescopy-2.jpgtrussescopy-1.jpg

Aerial View by Jeff Badgero

copy-of-view-above-july-4.jpgcopy-of-view-above-july.jpgA couple of shots taken by Jeff - thanks, Jeff!